Owner/Location
GAIL (India) Ltd./Dabhol-Bangalore-Goa
Mode of Execution
EDP, FEED & Project Management Services
Key Features
Dimensions:18” - 36”
Major Processing Units: Transportation of Regasified Liquid Natural Gas from Dabhol Terminal @ 92 kg/cm2g with overall capacity of 16 MMSCMD and maximum throughput of 22.04 MMSCMD.
Cost
Rs.5000 Crores
Schedule
42 Months
Procurement
- Total amount of free issue material Rs.1230 Crores.
- Total 86 no. vendors managed for procurement of free issue materials. Line pipes were ordered to 7 no. manufacturers and Line pipe supply had included logistics & dump site management.
Construction
Pipeline passed through Mangrove areas, which required permission from forest authorities for protection of flora and fauna.
HSE
No Loss Time Accident.
Cost Saving
Procurement of Line pipe and award of Contract for pipeline laying and construction Works done through reverse auction thereby achieving cost savings of ` 350 Crores for client.
Schedule Saving
Regasified liquid natural gas pipeline project commissioned 1 month ahead of schedule
Project Specific Achievement
Solar power has been used as the main power source for the stations.