Panipat Naphtha Cracker Project
  • Project Summary
  • Unique Challenges
  • Achievements
PNCP

Mode of Execution     
Pre FEED, FEED & PMC

Key Features    

Overall Capacity:
800 KTA Ethylene
660 KTA Propylene


Major Processing Units : 
HGU, Pyrolysis Gasoline Hydrogenation, Benzene Extraction Unit, PPU, LLDPE/HDPE Swing Unit, HDPE, Utility Boilers, Cooling Tower, DM Plant, Effluent Treatment Plant, O2/N2 Plant, Offsite Storage and Dispatch facility
      
Total Project Cost
USD 2.4 billion

Schedule
42 months
 

PNCP

Process & Engineering

 

  •     Zero Effluent discharge from the complex. Designed for 100% re-use of facility.
  •     Liquid effluent treatment conformed to the MINAS statutory Standards.


Procurement       
Procurement of following items through 54 nos Indian vendors and 18 nos foreign vendors

 

 

  •     300 nos of Equipments
  •     50 nos of Piping
  •     30 nos of Instrumentation
  •     17 nos of Electricals


 

PNCP

HSE
75 million Construction Man-hour achieved without Lost Time Accident.

Cost Saving
More than Rs.300 Crores savings to  client on estimated project cost after award of LSTK contract to NIL.

Schedule Saving

  • 128  days time saving w. r. t actual completion for world scale size naphtha cracker  complex.
  • Project completion in  46 months is the lowest time schedule at global level.